Deley causes of transmission line project in Vietnam : a case study of 500/220KV Hiep Hao - Pho Noi transmission line

AuthorNguyen Kim Cuong
NoteA thesis submitted in partial fulfillment of the requirements for the Degree of Master of Business Administration, School of Management
PublisherAsian Institute of Technology
AbstractDelay is one of the most common, important and serious problem which affect the time factor with relation to cost of project in the Construction field. In the large electrical project, especially transmission line project, the delay situation is not strange. It’s difficult to solve clearly the delay situation in the electrical project. But with the purpose of limiting delay time, and cost overrun, there are many studies find out the delay factors. Some factors which are subjective can be controlled and reduced time delay. This report summarized the cause of delay of the electrical projects in Vietnam. A case study of transmission line project will analyze more clearly the facing problems. Each problem shall be evaluate and promote method to reduce impact on the project. Finally, a framework of controlling and preventing delay in the future electrical project is suggested
Year2012
TypeThesis
SchoolSchool of Management (SOM)
DepartmentOther Field of Studies (No Department)
Academic Program/FoSMaster of Business Administration (MBA) (Publication code=SM)
Chairperson(s)Do Ba Khang;
Examination Committee(s)Vatcharapol Sukhotu;Claes, Marie-Therese ;
Scholarship Donor(s)Power Engineering Consulting Joint Stock Company No.1 (PECC1)-EVN Norwegian Electricity Cooperation (NEC);


Usage Metrics
View Detail0
Read PDF0
Download PDF0