Integer programming approach to solving the time-cost Tradeoff problem in construction | |
Author | Paitoon Visanuyothin |
Call Number | AIT Thesis no.ST-00-47 |
Subject(s) | Critical path analysis Integer programming Construction industry--Management |
Note | A thesis submitted in partial fulfillment of the requirements for the degree of Master of Engineering. |
Publisher | Asian Institute of Technology |
Abstract | Time-cost tradeoff analysis has been developed to support CPM for a long time. There have been many approaches proposed for the time-cost tradeoff analysis but those are not successfully accepted in the construction industry yet. The main objective of this study is to propose a new approach for time-cost tradeoff analysis. The new approach is based on Integer Programming (IP), which is a powerful tool for obtaining optimum results. Nine examples of time-cost tradeoff problem from various sources with different approaches used were taken and solved again by the new approach, named (-1 )-0-1 IP Approach. All results produced by the (-1 )-0-1 IP Approach were proved to be the same or better than results of those original approaches. This study also developed a computer program based on the (-1 )-0-1 IP Approach to facilitate its use. This study can be applied in construction resource selection before making a construction plan, which includes not only information on normal costs and normal durations but also crash costs and crash durations . |
Year | 2000 |
Type | Thesis |
School | School of Engineering and Technology (SET) |
Department | Department of Civil and Infrastucture Engineering (DCIE) |
Academic Program/FoS | Structural Engineering (STE) /Former Name = Structural Engineering and Construction (ST) |
Chairperson(s) | Manavazhi, Raj; |
Examination Committee(s) | Chotchai Charoenngam;Barry, William Joseph ; |
Scholarship Donor(s) | Asian Institute of Technology Partial Scholarship; |
Degree | Thesis (M.Eng.) - Asian Institute of Technology, 2000 |