Non-shield tunneling at the MRTA initial system project

AuthorBraune, Marko
Call NumberAIT Thesis no. GE-00-05
Subject(s)Tunneling--Thailand--Bangkok
Subways--Thailand--Bangkok

NoteA thesis submitted in partial fulfillment of the requirements for the degree of Master of Engineering, School of Engineering and Technology
PublisherAsian Institute of Technology
Series StatementThesis ; no. GE-00-05
AbstractThe first heavy rail underground train in Bangkok, the Blue Line or Chaloem Ratchamongkhon Line for the Mass Rapid Transit System is unique because of the local present ground condition. It is a challenge for all companies and engineers working on that project to let it become a success and set the foundation stone for further tunnel projects and also more underground railway lines in Bangkok and Thailand. This research reviews the different applied methods for ground treatment and construction and their effectiveness as well as some of the design principles required for every construction. The results are summarized related to the local present geological condition, construction design and layout, which have given every construction their own characteristics. This is composed of especially intervention shaft and cross passages constructions, station and entrance structures, pump sump constructions and the depot approach ramp.
Year2001
Corresponding Series Added EntryAsian Institute of Technology. Thesis ; no. GE-00-05
TypeThesis
SchoolSchool of Engineering and Technology (SET)
DepartmentDepartment of Civil and Infrastucture Engineering (DCIE)
Academic Program/FoSGeotechnical Engineering (GE)
Chairperson(s)Noppadol Phienwej;
Examination Committee(s)Balasubramaniarn, A.S.;Miura, Kinya;
Scholarship Donor(s)European Commission (PTS - Program);
DegreeThesis (M.Eng.) - Asian Institute of Technology, 2001