Uncertainty evaluation of tunnelling in the Bhumibol Reservoir Inflow Augmentation Project | |
Author | Nunthanis Wongvatana |
Call Number | AIT Thesis no.GE-05-12 |
Subject(s) | Bhumibol Reservoir Inflow Augmentation Project Tunneling--Evaluation--Thailand--Bhumibol Reservoir |
Note | A thesis submitted in partial fulfillment of the requirements for the degree of Master of Engineering, School of Engineering and Technology |
Publisher | Asian Institute of Technology |
Series Statement | Thesis ; no. GE-05-12 |
Abstract | On the basis of various scenarios of simulated rock mass condition using Monte Carlo random variable simulation method a comparative study was made for tunnelling at the Bhumibol Reservoir Inflow Augmentation Project. The geological conditions were interpreted from borehole data and geological map by mean of geological parameters ,index: Rock Mass Type (RMT) and the Geotechnical units (GTU) throughout the tunnel length. The geological parameter used after the simulation is the Geological Strength Index (GSI) and the equivalent Rock Mass Rating (RMR) for tunnelling with Tunnel Boring Machine (TBM) and Drill and Blast (D&B) methods were determined for rock support requirement determination. Then the cost of tunnelling (excavation plus rock support cost) for three scenarios of expected rock mass condition (most likelihood, pessimistic and optimistic) were determined. |
Year | 2005 |
Corresponding Series Added Entry | Asian Institute of Technology. Thesis ; no. GE-05-12 |
Type | Thesis |
School | School of Engineering and Technology (SET) |
Department | Other Field of Studies (No Department) |
Academic Program/FoS | Geotechnical Engineering (GE) |
Chairperson(s) | Noppadol Phien-wej;Sutthisak Soralump; |
Examination Committee(s) | Bergado, Dennes T.; Park, Kyung-Ho ; |
Scholarship Donor(s) | Asian Institute of Technology Fellowship; |
Degree | Thesis (M.Eng.) - Asian Institute of Technology, 2005 |