Delay management in road projects of the department of rural road development : a case of Inn Mai Ho Gyang-Man Htam-Hway Khoat-Tone Sein Lon road project in Myanmar | |
| Author | Zay Ya Win |
| Call Number | AIT Proj. no.MPM-MM-CM-23-03 |
| Subject(s) | Rural roads--Management--Myanmar--Case studies Production scheduling--Myanmar--Case studies |
| Note | A project submitted in partial fulfillment of the requirements for the degree of Master of Engineering (Professional) in Construction Engineering and Infrastructure Management |
| Publisher | Asian Institute of Technology |
| Abstract | Construction delays are frequently the result of poorly managed event(s) and can be seen as a risk for the projects if identified, analyzed, and managed in a systematic process at inception. This would allow for the management, minimization, sharing, mitigation, or acceptance of the risk to produce some positive results and reduce the likelihood of further delay. In terms of the development of antagonistic relationships, distrust, litigation, arbitration, and cash-flow issues, delays in construction projects have a detrimental impact on clients, contractors, and consultants. Until a building project meets the financial, time, and quality constraints imposed on it, it cannot be considered a successful undertaking. However, it happens frequently for a construction project to fall short of completing its task within the required budget, timeframe, and level of quality. The field of "Project management" is used to oppose the unanticipated delays in advance, which aids in minimizing the delays. Application of knowledge, skill, tools, and methods to project activities in order to fulfill project requirements is project management, which necessitates the efficient supervision of the project procedure of management. In Myanmar, the management systems in construction still require a new set of techniques and technologies to manage projects and project delays. This study provides the techniques of delay management to mitigate delay for future reference. |
| Year | 2023 |
| Type | Project |
| School | School of Engineering and Technology |
| Department | Department of Civil and Infrastucture Engineering (DCIE) |
| Academic Program/FoS | Construction Engineering and Infrastructure Manangement in Myanmar (Professional Master) (MPM-MM-CM) |
| Chairperson(s) | Hadikusumo, Bonaventura H. W. |
| Examination Committee(s) | Chotchai Charoenngam;Wasan Teerajetgul |
| Degree | Project (M. Eng.) - Asian Institute of Technology, 2023 |